Construction Starts April 8 on High School’s New Field and Track

96
0
SHARE

After months of waiting and anticipating, two weeks from this morning, formal construction of the new synthetic field and track at Culver City High School will begin.

Here are the key dates, starting this week:

Thursday evening at 7 – Community meeting, Multi-Purpose Room, Culver City Middle School.


Wednesday, April 3 – Mobilization of site, installation of temporary fencing and other materials.

Monday, April 8 –Increment 1, start of construction. 

“Our athletic fields at the Middle School-High School complex are used by thousands of students every week,” said President Kathy Paspalis of the School Board. “I'm thrilled renovations finally are under way.”

Ms. Paspalis said she has been assured that large portions of the projects will be available when the new term begiuns in September.

Balfour Beatty Construction is the School District's new general contracting partner, working with architect Westberg + White. The company's scope of work includes constructing a new synthetic grass football field and a new synthetic track at Culver City High School. In addition, the project team will be working with the District's solar consultant and Westberg + White to assist with the coordination of the future solar project at the high school, Middle School and Farragut Elementary.

Balfour Beatty has built similar athletic track and field construction projects for a large number of California school districts statewide.

For questions, Gary Nenadal may be contacted at 310.415.6655 or at  gnenadal@balfourbeattyus.com